Collect work products, measures, measurement results, and improvement information derived from planning and performing the product integration process to support the future use and improvement of the organization's processes and
process assets.
Elaboration:
Examples of work products, measures, measurement results, and improvement information include the following:
· Records of the receipt of product components, exception reports, confirmation of configuration status, and results of readiness checking
· Percent of total development effort spent in product integration (actual to date plus estimate to complete)
· Defects found in the product and test environment during product integration
· Problem reports resulting from product integration