Identify and involve the relevant stakeholders of the project planning process as planned.
Elaboration:
Refer to Table 6.2 on page 95 in Generic Goals and Generic Practices for more information about the relationship between generic practice 2.7 and the Plan Stakeholder Involvement practice in the Project Planning process
area.
Examples of activities for stakeholder involvement include the following:
· Establishing estimates
· Reviewing and resolving issues on the completeness and correctness of the project risks
· Reviewing data management plans
· Establishing project plans
· Reviewing project plans and resolving issues on work and resource issues