Collect and analyze the issues and determine the corrective actions necessary to address the issues.
Typical Work Products
1. List of issues needing corrective actions
Subpractices
1. Gather issues for analysis.
Issues are collected from reviews and the execution of other processes.
Examples of issues to be gathered include the following:
· Issues discovered through performing verification and validation activities
· Significant deviations in the project planning parameters from the estimates in the project plan
· Commitments (either internal or external) that have not been satisfied
· Significant changes in risk status
· Data access, collection, privacy, or security issues
· Stakeholder representation or involvement issues
2. Analyze issues to determine need for corrective action.
Refer to the Project Planning process area for information about corrective action criteria.
Corrective action is required when the issue, if left unresolved, may prevent the project from meeting its objectives.