Review the accomplishments and results of the project at selected project milestones.
Refer to the Project Planning process area for more information about milestone planning.
Milestone reviews are planned during project planning and are typically formal reviews.
Typical Work Products
1. Documented milestone review results
Subpractices
1. Conduct reviews at meaningful points in the project’s schedule, such as the completion of selected stages, with relevant stakeholders.
Managers, staff members, customers, end users, suppliers, and other relevant stakeholders within the organization are included in the milestone reviews as appropriate.
2. Review the commitments, plan, status, and risks of the project.
3. Identify and document significant issues and their impacts.
4. Document the results of the review, action items, and decisions.
5. Track action items to closure.