 SP 1.2 Monitor Commitments
Process AreaPMC
Level2
GoalSG 1
PracticeSP 1.2

Monitor commitments against those identified in the project plan.

Resource commitments that result in expenditures (e.g., issued purchase orders and completed supplier deliverables that are accepted) are tracked when the expense is incurred, even prior to formal payment, to ensure that future financial and legal obligations are accounted for as soon as they are incurred. Commitments that do not result in expenditures (e.g., allocation of resources or skill sets) should also be monitored.

Supplier commitments for the project are also monitored by the acquirer through these practices.

Typical Work Products

1.    Records of commitment reviews

Subpractices

1.    Regularly review commitments (both external and internal).

2.    Identify commitments that have not been satisfied or are at significant risk of not being satisfied.

3.    Document the results of commitment reviews.

Table  | Images  | Glossary  | Index  | Faceted index


Process
Areas(continuous)

Process
management  
 OPF
 OPD
 OT  
 OPP 
 OID
Project
management
 PP
 PMC
 IPM
 QPM
 RSKM
 REQM
Acquisition
 AM
 SSAD 
 ARD
 ATM
 AVER
 AVAL
Support
 CM
 PPQA
 MA
 DAR
 CAR