 SP 2.4 Plan for Project Resources
Process AreaPP
Level2
GoalSG 2
PracticeSP 2.4

Plan for necessary resources to perform the project.

  

IPPD Addition

When integrated teams are formed, planning for project resources should consider staffing of the integrated teams.

  

Defining project resources (labor, machinery/equipment, materials, and methods) and quantities needed to perform project activities builds on the initial estimates and provides additional information that can be applied to expand the WBS used to manage the project.

The top-level WBS developed earlier as an estimation mechanism is typically expanded by decomposing these top levels into work packages that represent singular work units that can be separately assigned, performed, and tracked. This subdivision is done to distribute management responsibility and provide better management control. Each work package or work product in the WBS should be assigned a unique identifier (e.g., number) to permit tracking. A WBS can be based on requirements, activities, work products, or a combination of these items. A dictionary that describes the work for each work package in the WBS should accompany the work breakdown structure.

Typical Work Products

1.    WBS work packages

2.    WBS task dictionary

3.    Staffing requirements based on project size and scope

4.    Critical facilities/equipment list

5.    Process/workflow definitions and diagrams

6.    Program administration requirements list

Subpractices

1.    Determine process requirements.

The processes used to manage a project must be identified, defined, and coordinated with all the relevant stakeholders to ensure efficient operations during project execution.

2.    Determine staffing requirements.

The staffing of a project depends on the decomposition of the project requirements into tasks, roles, and responsibilities for accomplishing the project requirements as laid out within the work packages of the WBS.

Staffing requirements must consider the knowledge and skills required for each of the identified positions, as defined in the Plan for Needed Knowledge and Skills specific practice.

3.    Determine facilities, equipment, and component requirements.

Most projects are unique in some sense and require some set of unique assets to accomplish the objectives of the project. The determination and acquisition of these assets in a timely manner are crucial to project success.

Lead-time items need to be identified early to determine how they will be addressed. Even when the required assets are not unique, compiling a list of all of the facilities, equipment, and parts (e.g., number of computers for the personnel working on the project, software applications, and office space) provides insight into aspects of the scope of an effort that are often overlooked.

Table  | Images  | Glossary  | Index  | Faceted index


Process
Areas
(continuous)


Process
management  
 
OPF
 OPD
 OT  
 
OPP 
 
OID
Project
management
 
PP
 PMC
 SAM 
 
IPM
 RSKM
 
QPM
Engineering
 
RD
 RM
 TS
 PI
 VE
 VA
Support
 
CM
 PPQA
 MA
 
DAR
 CAR