 SP 2.5 Plan for Needed Knowledge and Skills
Process AreaPP
Level2
GoalSG 2
PracticeSP 2.5

Plan for knowledge and skills needed to perform the project.

Refer to the Organizational Training process area for more information about knowledge and skills information to be incorporated into the project plan.

Knowledge delivery to projects involves both training of project personnel and acquisition of knowledge from outside sources.

Staffing requirements are dependent on the knowledge and skills available to support the execution of the project.

Typical Work Products

1.    Inventory of skill needs

2.    Staffing and new hire plans

3.    Databases (e.g., skills and training)

Subpractices

1.    Identify the knowledge and skills needed to perform the project.

2.    Assess the knowledge and skills available.

3.    Select mechanisms for providing needed knowledge and skills.

Example mechanisms include the following:

·   In-house training (both organizational and project)

·   External training

·   Staffing and new hires

·   External skill acquisition

  

The choice of in-house training or outsourced training for the needed knowledge and skills is determined by the availability of training expertise, the project’s schedule, and the business objectives.

4.    Incorporate selected mechanisms into the project plan.

Table  | Images  | Glossary  | Index  | Faceted index


Process
Areas
(continuous)


Process
management  
 
OPF
 OPD
 OT  
 
OPP 
 
OID
Project
management
 
PP
 PMC
 SAM 
 
IPM
 RSKM
 
QPM
Engineering
 
RD
 RM
 TS
 PI
 VE
 VA
Support
 
CM
 PPQA
 MA
 
DAR
 CAR