Obtain commitment from relevant stakeholders responsible for performing and supporting plan execution.
Obtaining commitment involves interaction among all relevant stakeholders, both internal and external to the project. The individual or group making a commitment should have confidence that
the work can be performed within cost, schedule, and performance constraints. Often, a provisional commitment is adequate to allow the effort to begin and to permit research to be performed to increase confidence to the appropriate level needed to
obtain a full commitment.
Typical Work Products
1. Documented requests for commitments
2. Documented commitments
Subpractices
1. Identify needed support and negotiate commitments with relevant stakeholders.
The WBS can be used as a checklist for ensuring that commitments are obtained for all tasks.
The plan for stakeholder interaction should identify all parties from whom commitment should be obtained.
2. Document all organizational commitments, both full and provisional, ensuring the appropriate level of
signatories.
Commitments must be documented to ensure a consistent mutual understanding and for tracking and maintenance. Provisional commitments should be accompanied by a description of risks associated
with the relationship.
3. Review internal commitments with senior management, as appropriate.
4. Review external commitments with senior management, as appropriate.
Management may have the necessary insight and authority to reduce risks associated with external commitments.
5. Identify commitments regarding interfaces between project elements and other projects and organizational units so that these
commitments can be monitored.
Well-defined interface specifications form the basis for commitments.