 SP 1.3 Conduct Technical Reviews
Process AreaATM
Level3
GoalSG 1
PracticeSP 1.3

Conduct technical reviews with the supplier as defined in the supplier agreement.

Technical reviews are used by the acquirer to confirm that products and services being developed or produced by suppliers meet user needs and requirements.

Technical reviews should have the following characteristics:

·         Conducted when the technical solution under development satisfies review entry criteria (i.e., event driven, not schedule driven)

·         At a minimum, conducted at the transition from one acquisition phase to the next and at major transition points of technical effort

·         Have their processes and requirements addressed in and required by the supplier agreement

Typically, the project’s technical plan (e.g., the systems engineering management plan) documents the timing, conduct, entrance criteria, and success or exit criteria used for technical reviews.

 

Refer to the Project Planning process area for more information about planning the technical aspects of the project.

Technical reviews typically include the following activities:

·         Reviewing the supplier’s technical activities and verifying that the supplier’s interpretation and implementation of requirements are consistent with the acquirer’s interpretation

·         Ensuring that technical commitments are being met and that technical issues are communicated and resolved in a timely manner

·         Obtaining technical information about the supplier’s products

·         Providing the supplier with insight into customer and end user expectations and requirements

·         Providing appropriate technical information and support to the supplier

 

Examples of technical reviews that can be conducted include the following:

·         Initial Technical Review (ITR)

·         Alternative System Review (ASR)

·         Integrated Baseline Review (IBR)

·         Technology Readiness Assessment (TRA)

·         System Requirements Review (SRR)

·         System Functional Review (SFR)

·         Preliminary Design Review (PDR)

·         Critical Design Review (CDR)

·         Test Readiness Review (TRR)

·         System Verification Review (SVR)

·         Production Readiness Review (PRR)

·         Operational Test Readiness Review (OTRR)

·         Physical Configuration Audit (PCA)

 

Typical Work Products

1.    Review schedule

2.    Entry and exit criteria

3.    Review results

4.    Documented issues (e.g., issues with customer requirements, product and product component requirements, product architecture, and product design)

Typical Supplier Deliverables

1.    Progress reports and process, product, and service level measurements

2.    Technical performance measurements

3.    Review materials and reports

4.    Action items tracked to closure

5.    Documentation of product and document deliveries

Subpractices

1.    Identify participants for the technical review.

2.    Conduct the technical review.

3.    Analyze and record results of the review.

4.    Use the results of technical reviews to improve the supplier’s technical solution.

The results of some reviews may require changes to the supplier agreement.

Refer to the Solicitation and Supplier Agreement Development process area for more information about establishing and maintaining the supplier agreement.

Table  | Images  | Glossary  | Index  | Faceted index


Process
Areas(continuous)

Process
management  
 OPF
 OPD
 OT  
 OPP 
 OID
Project
management
 PP
 PMC
 IPM
 QPM
 RSKM
 REQM
Acquisition
 AM
 SSAD 
 ARD
 ATM
 AVER
 AVAL
Support
 CM
 PPQA
 MA
 DAR
 CAR