 SP 1.4 Integrate Plans
Process AreaIPM
Level3
GoalSG 1
PracticeSP 1.4

Integrate the project plan and other plans that affect the project to describe the project’s defined process.

Refer to the Project Planning process area for more information about establishing and maintaining a project plan.

Refer to the Organizational Process Definition process area for more information about organizational process assets and, in particular, the organization’s measurement repository.

Refer to the Organizational Process Focus process area for more information about organizational process needs and objectives.

This specific practice extends the specific practices for establishing and maintaining a project plan to address additional planning activities such as incorporating the project’s defined process, coordinating with relevant stakeholders, using organizational process assets, incorporating plans for peer reviews, and establishing objective entry and exit criteria for tasks.

The development of the project plan should account for current and projected needs, objectives, and requirements of the organization, customer, suppliers, and end users, as appropriate.

Typical Work Products

1.    Integrated plans

Typical Supplier Deliverables

1.    Supplier plans

Subpractices

1.    Integrate other plans that affect the project with the project plan.

Other plans that affect the project plan may include the following:

·       Quality assurance plans

·       Configuration management plans

·       Risk management strategy

·       Documentation plans

 

2.    Incorporate into the project plan the definitions of measures and measurement activities for managing the project.

Refer to the Measurement and Analysis process area for more information about defining measures and measurement activities and analyzing measurement data.

3.    Identify and analyze product and project interface risks.

Refer to the Risk Management process area for more information about identifying and analyzing risks.

4.    Schedule tasks in a sequence that accounts for critical development factors and project risks.

Examples of factors considered in scheduling include the following:

·       Size and complexity of tasks

·       Needs of the customer and end users

·       Availability of critical resources

·       Availability of key personnel

 

5.    Incorporate plans for performing peer reviews on work products of the project’s defined process.

6.    Incorporate the training needed to perform the project’s defined process in the project’s training plans.

7.    Establish objective entry and exit criteria to authorize the initiation and completion of tasks described in the work breakdown structure (WBS).

Refer to the Project Planning process area for more information about the WBS.

8.    Ensure that the project plan is appropriately compatible with the plans of relevant stakeholders.

9.    Identify how conflicts will be resolved that arise among relevant stakeholders.

Refer to the Agreement Management process area for more information about resolving supplier agreement issues.

Table  | Images  | Glossary  | Index  | Faceted index


Process
Areas(continuous)

Process
management  
 OPF
 OPD
 OT  
 OPP 
 OID
Project
management
 PP
 PMC
 IPM
 QPM
 RSKM
 REQM
Acquisition
 AM
 SSAD 
 ARD
 ATM
 AVER
 AVAL
Support
 CM
 PPQA
 MA
 DAR
 CAR